Prior to commencing excavation around an older commercial building in British Columbia, an excavator operator discovers unmarked utility lines within the planned excavation area. What is the immediate and most appropriate action the operator should take?
Upon discovering unmarked utilities, the excavator operator's primary responsibility is to stop work immediately and contact the relevant provincial one-call se
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: Prior to commencing excavation around an older commercial building in British Columbia, an excavator operator discovers unmarked utility lines within the planned excavation area. What is the immediate and most appropriate action the operator should take?
Answer options:
- Proceed with extreme caution, hand digging in the immediate vicinity of the unmarked lines.
- Attempt to contact the building owner for information on the utility layout. ✅ Stop all excavation work immediately and contact BC One Call (BC 1 Call) again for further assistance.
- Use ground-penetrating radar (GPR) to identify the exact location and depth of the lines.
Correct answer: Stop all excavation work immediately and contact BC One Call (BC 1 Call) again for further assistance.
Explanation: Upon discovering unmarked utilities, the excavator operator's primary responsibility is to stop work immediately and contact the relevant provincial one-call service (BC 1 Call in this instance). Proceeding with excavation, even cautiously, risks damaging utilities and endangering workers. Contacting the building owner without consulting the utility locate service first is not the correct procedure, and using GPR is a specialized task typically performed by utility locators, not the excavator operator.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.