Excavator Operator Certification Exam Prep · Question
According to CSA Z150-16, when an excavator is left unattended overnight on a construction site, what specific measure MUST be implemented beyond shutting down the engine and lowering attachments?
CSA Z150-16 stipulates that controls accessible to unauthorized persons must be locked to prevent accidental starting or theft, ensuring the machine cannot be o
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: According to CSA Z150-16, when an excavator is left unattended overnight on a construction site, what specific measure MUST be implemented beyond shutting down the engine and lowering attachments?
Answer options:
- The machine must be covered with a tarp to protect it from weather. ✅ All accessible controls must be locked to prevent unauthorized operation.
- A 'Do Not Operate' tag must be placed on the ignition key.
- The machine must be positioned on a slight incline to prevent fluid pooling.
Correct answer: All accessible controls must be locked to prevent unauthorized operation.
Explanation: CSA Z150-16 stipulates that controls accessible to unauthorized persons must be locked to prevent accidental starting or theft, ensuring the machine cannot be operated inadvertently when left unattended.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses