A typical excavation project requires moving 100 loose cubic metres (LCM) of material. If the soil has a swell factor of 25%, how many bank cubic metres (BCM) did the excavation originally comprise?
To find the Bank Cubic Metres (BCM) from Loose Cubic Metres (LCM) given a swell factor, use the formula: BCM = LCM / (1 + Swell Factor). So, BCM = 100 LCM / (1
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
Question: A typical excavation project requires moving 100 loose cubic metres (LCM) of material. If the soil has a swell factor of 25%, how many bank cubic metres (BCM) did the excavation originally comprise?
Answer options: ✅ 80 BCM
- 75 BCM
- 100 BCM
- 125 BCM
Correct answer: 80 BCM
Explanation: To find the Bank Cubic Metres (BCM) from Loose Cubic Metres (LCM) given a swell factor, use the formula: BCM = LCM / (1 + Swell Factor). So, BCM = 100 LCM / (1 + 0.25) = 100 / 1.25 = 80 BCM. This reflects the original volume of material before excavation.
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
More about Heavy Equipment Operator Certification Exam Prep
Related Questions
More for Heavy Equipment Operator Certification Exam Prep candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Heavy Equipment Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.