A trench needs to be backfilled with 300 loose cubic metres (LCM) of material. If the material compacts to 90% of its loose volume, how many compacted cubic metres (CCM) will the trench contain?

To calculate the compacted volume, multiply the loose volume by the compaction percentage. So, 300 LCM × 0.90 = 270 CCM. This represents the final volume after

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

Question: A trench needs to be backfilled with 300 loose cubic metres (LCM) of material. If the material compacts to 90% of its loose volume, how many compacted cubic metres (CCM) will the trench contain?

Answer options: ✅ 270 CCM

  • 300 CCM
  • 330 CCM
  • 315 CCM

Correct answer: 270 CCM

Explanation: To calculate the compacted volume, multiply the loose volume by the compaction percentage. So, 300 LCM × 0.90 = 270 CCM. This represents the final volume after compaction.

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

More about Heavy Equipment Operator Certification Exam Prep

Related Questions

More for Heavy Equipment Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Heavy Equipment Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.