A trench needs to be backfilled with 300 loose cubic metres (LCM) of material. If the material compacts to 90% of its loose volume, how many compacted cubic metres (CCM) will the trench contain?
To calculate the compacted volume, multiply the loose volume by the compaction percentage. So, 300 LCM × 0.90 = 270 CCM. This represents the final volume after
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
Question: A trench needs to be backfilled with 300 loose cubic metres (LCM) of material. If the material compacts to 90% of its loose volume, how many compacted cubic metres (CCM) will the trench contain?
Answer options: ✅ 270 CCM
- 300 CCM
- 330 CCM
- 315 CCM
Correct answer: 270 CCM
Explanation: To calculate the compacted volume, multiply the loose volume by the compaction percentage. So, 300 LCM × 0.90 = 270 CCM. This represents the final volume after compaction.
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
More about Heavy Equipment Operator Certification Exam Prep
Related Questions
More for Heavy Equipment Operator Certification Exam Prep candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Heavy Equipment Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.