An operator is loading a material with a 2.5 cubic metre (m³) struck capacity bucket. Due to the sticky nature of the clay, the bucket achieves only 85% of its struck capacity in actual material volume per pass. What is the actual volume of material being moved per pass?
The actual volume is calculated by multiplying the struck capacity by the fill factor. If the bucket achieves only 85% of its struck capacity, then the actual v
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
Question: An operator is loading a material with a 2.5 cubic metre (m³) struck capacity bucket. Due to the sticky nature of the clay, the bucket achieves only 85% of its struck capacity in actual material volume per pass. What is the actual volume of material being moved per pass?
Answer options: ✅ 2.125 m³
- 2.500 m³
- 2.875 m³
- 3.000 m³
Correct answer: 2.125 m³
Explanation: The actual volume is calculated by multiplying the struck capacity by the fill factor. If the bucket achieves only 85% of its struck capacity, then the actual volume is 2.5 m³ * 0.85 = 2.125 m³. This indicates a poor fill due to material characteristics.
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
More about Heavy Equipment Operator Certification Exam Prep
Related Questions
More for Heavy Equipment Operator Certification Exam Prep candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Heavy Equipment Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.