An excavation measures 15 metres long, 8 metres wide, and 3 metres deep. If the soil has a swell factor of 25%, what is the bank cubic volume (BCM) of material to be excavated?
The bank cubic volume is calculated directly from the excavation dimensions: 15 m * 8 m * 3 m = 360 BCM. The swell factor is used for loose cubic volume calcula
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
Question: An excavation measures 15 metres long, 8 metres wide, and 3 metres deep. If the soil has a swell factor of 25%, what is the bank cubic volume (BCM) of material to be excavated?
Answer options: ✅ 360 BCM
- 288 BCM
- 450 BCM
- 300 BCM
Correct answer: 360 BCM
Explanation: The bank cubic volume is calculated directly from the excavation dimensions: 15 m * 8 m * 3 m = 360 BCM. The swell factor is used for loose cubic volume calculations, not bank volume. (Reference: OPSWA HEO Curriculum, Earthmoving Math Module).
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
More about Heavy Equipment Operator Certification Exam Prep
Related Questions
More for Heavy Equipment Operator Certification Exam Prep candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Heavy Equipment Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.