A trench is 50 metres long, 1.2 metres wide, and 2.5 metres deep. If the soil's swell factor is 20%, what is the loose cubic volume (LCM) of material that needs to be hauled away?

First, calculate the bank cubic volume (BCM): 50 m * 1.2 m * 2.5 m = 150 BCM. Then, apply the swell factor: 150 BCM * (1 + 0.20) = 180 LCM. (Reference: IUOE 793

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

Question: A trench is 50 metres long, 1.2 metres wide, and 2.5 metres deep. If the soil's swell factor is 20%, what is the loose cubic volume (LCM) of material that needs to be hauled away?

Answer options:

  • 150 LCM ✅ 180 LCM
  • 120 LCM
  • 135 LCM

Correct answer: 180 LCM

Explanation: First, calculate the bank cubic volume (BCM): 50 m * 1.2 m * 2.5 m = 150 BCM. Then, apply the swell factor: 150 BCM * (1 + 0.20) = 180 LCM. (Reference: IUOE 793 Training Standards, Earthmoving Calculations).

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

More about Heavy Equipment Operator Certification Exam Prep

Related Questions

More for Heavy Equipment Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Heavy Equipment Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.