An excavator loads a truck with 12 buckets. Each bucket holds 2.25 cubic metres (BCM). If the swell factor of the material is 30%, what is the total loose cubic volume (LCM) loaded into the truck?
First, calculate the total bank cubic volume (BCM): 12 buckets * 2.25 BCM/bucket = 27 BCM. Then, convert to loose cubic metres (LCM) by applying the swell facto
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
Question: An excavator loads a truck with 12 buckets. Each bucket holds 2.25 cubic metres (BCM). If the swell factor of the material is 30%, what is the total loose cubic volume (LCM) loaded into the truck?
Answer options:
- 27 LCM ✅ 35.1 LCM
- 20.7 LCM
- 30.8 LCM
Correct answer: 35.1 LCM
Explanation: First, calculate the total bank cubic volume (BCM): 12 buckets * 2.25 BCM/bucket = 27 BCM. Then, convert to loose cubic metres (LCM) by applying the swell factor: 27 BCM * (1 + 0.30) = 27 BCM * 1.30 = 35.1 LCM. (Reference: OPSWA HEO Curriculum, Earthmoving Math Module).
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
More about Heavy Equipment Operator Certification Exam Prep
Related Questions
More for Heavy Equipment Operator Certification Exam Prep candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Heavy Equipment Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.