An excavator loads a truck with 12 buckets. Each bucket holds 2.25 cubic metres (BCM). If the swell factor of the material is 30%, what is the total loose cubic volume (LCM) loaded into the truck?

First, calculate the total bank cubic volume (BCM): 12 buckets * 2.25 BCM/bucket = 27 BCM. Then, convert to loose cubic metres (LCM) by applying the swell facto

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

Question: An excavator loads a truck with 12 buckets. Each bucket holds 2.25 cubic metres (BCM). If the swell factor of the material is 30%, what is the total loose cubic volume (LCM) loaded into the truck?

Answer options:

  • 27 LCM ✅ 35.1 LCM
  • 20.7 LCM
  • 30.8 LCM

Correct answer: 35.1 LCM

Explanation: First, calculate the total bank cubic volume (BCM): 12 buckets * 2.25 BCM/bucket = 27 BCM. Then, convert to loose cubic metres (LCM) by applying the swell factor: 27 BCM * (1 + 0.30) = 27 BCM * 1.30 = 35.1 LCM. (Reference: OPSWA HEO Curriculum, Earthmoving Math Module).

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

More about Heavy Equipment Operator Certification Exam Prep

Related Questions

More for Heavy Equipment Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Heavy Equipment Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.