Heavy Equipment Operator Certification Exam Prep · Question

Before any ground disturbance is initiated on a construction site in Ontario, what is the mandatory minimum notice period for requesting utility locates through Ontario One Call?

According to Ontario Regulation 213/91 (Construction Projects), section 228 (1), a person shall not excavate or dig for the purpose of a ground disturbance unle

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

Question: Before any ground disturbance is initiated on a construction site in Ontario, what is the mandatory minimum notice period for requesting utility locates through Ontario One Call?

Answer options: ✅ At least 5 business days, excluding the day of excavation

  • At least 3 business days, including the day of excavation
  • At least 24 hours, excluding weekends
  • At least 48 hours, including statutory holidays

Correct answer: At least 5 business days, excluding the day of excavation

Explanation: According to Ontario Regulation 213/91 (Construction Projects), section 228 (1), a person shall not excavate or dig for the purpose of a ground disturbance unless at least 5 business days' notice of the excavation or digging has been provided to the operators of underground infrastructure.

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

More about Heavy Equipment Operator Certification Exam Prep

Related Questions

More for Heavy Equipment Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Heavy Equipment Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.