Skip to main content

Plumber Red Seal · Question

A trench is being excavated for a new water line in unstable, sandy soil. The trench is currently 2.5 metres deep. What is the required minimum distance that excavated material (spoil pile) must be kept from the edge of the trench?

Excavated material (spoil pile) must be kept at least 1 metre (3 feet) back from the edge of the trench to prevent it from falling back in and to reduce the sur

Start free practice for Plumber Red Seal

177 questions · no signup required · 40 free questions per day

Start Practice →

Question: A trench is being excavated for a new water line in unstable, sandy soil. The trench is currently 2.5 metres deep. What is the required minimum distance that excavated material (spoil pile) must be kept from the edge of the trench?

Answer options: ✅ At least 1.0 metre from the edge of the trench.

  • At least half the depth of the trench, so 1.25 metres.
  • As far back as possible, but no less than 0.6 metres.
  • Only enough to prevent it from falling back into the trench, typically 0.3 metres.

Correct answer: At least 1.0 metre from the edge of the trench.

Explanation: Excavated material (spoil pile) must be kept at least 1 metre (3 feet) back from the edge of the trench to prevent it from falling back in and to reduce the surcharge load on the trench walls, which can contribute to collapses, especially in unstable soil. Other distances stated are incorrect or inadequate for safety.

Start free practice for Plumber Red Seal

177 questions · no signup required · 40 free questions per day

Start Practice →

More about Plumber Red Seal

Related Questions

More for Plumber Red Seal candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Plumber Red Seal Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.