PMP (Project Management Professional) · Question

What is the main purpose of the 'Develop Project Management Plan' process?

The Develop Project Management Plan process is about defining, preparing, and coordinating all subsidiary plans and baselines, thus creating a comprehensive pro

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the main purpose of the 'Develop Project Management Plan' process?

Answer options:

  • To execute the project work ✅ To define and integrate all project plans
  • To obtain formal project authorization
  • To control changes to the project

Correct answer: To define and integrate all project plans

Explanation: The Develop Project Management Plan process is about defining, preparing, and coordinating all subsidiary plans and baselines, thus creating a comprehensive project management plan.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.