What is the primary purpose of the 'Control Costs' process?

Control Costs focuses on monitoring, tracking, and managing changes to the cost baseline and overall project budget.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the primary purpose of the 'Control Costs' process?

Answer options: ✅ Monitoring the status of the project to update the project budget and managing changes to the cost baseline

  • Estimating the cost of all resources needed to complete project activities
  • Aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline
  • Determining the policies, procedures, and documentation that will be used for planning, managing, expending, and controlling project costs

Correct answer: Monitoring the status of the project to update the project budget and managing changes to the cost baseline

Explanation: Control Costs focuses on monitoring, tracking, and managing changes to the cost baseline and overall project budget.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.