Which of the following is an input to the 'Determine Budget' process?

Activity Cost Estimates are an input to the 'Determine Budget' process, which aggregates these estimates to establish a cost baseline.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which of the following is an input to the 'Determine Budget' process?

Answer options:

  • Cost Baseline ✅ Activity Cost Estimates
  • Funding Requirements
  • Project Funding Requirements

Correct answer: Activity Cost Estimates

Explanation: Activity Cost Estimates are an input to the 'Determine Budget' process, which aggregates these estimates to establish a cost baseline.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.