When should 'contingency reserves' be used in a project?

Contingency reserves are funds, time, or resources allocated for known risks that may or may not occur (known-unknowns).

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: When should 'contingency reserves' be used in a project?

Answer options:

  • To cover unexpected scope changes requested by stakeholders
  • To fund identified and accepted risks
  • To pay for general management activities not directly related to the project ✅ To address known-unknowns or anticipated risks

Correct answer: To address known-unknowns or anticipated risks

Explanation: Contingency reserves are funds, time, or resources allocated for known risks that may or may not occur (known-unknowns).

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.