In schedule management, what is 'crashing'?

Crashing is a schedule compression technique where resources are added to shorten the project duration for the least incremental cost.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: In schedule management, what is 'crashing'?

Answer options: ✅ Adding resources to shorten project duration for the least incremental cost

  • Reducing project scope to meet deadlines
  • Delaying the start of less critical activities
  • Removing tasks that are not on the critical path

Correct answer: Adding resources to shorten project duration for the least incremental cost

Explanation: Crashing is a schedule compression technique where resources are added to shorten the project duration for the least incremental cost.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.