Which scheduling method is used to determine the earliest and latest possible start and finish times for uncompleted portions of project activities?

CPM is a technique that uses forward and backward passes through the network diagram to calculate activity start and finish dates and identify the critical path

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which scheduling method is used to determine the earliest and latest possible start and finish times for uncompleted portions of project activities?

Answer options: ✅ Critical Path Method (CPM)

  • Resource Leveling
  • Fast Tracking
  • Crashing

Correct answer: Critical Path Method (CPM)

Explanation: CPM is a technique that uses forward and backward passes through the network diagram to calculate activity start and finish dates and identify the critical path.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.