Which tool or technique is used to determine the earliest and latest possible start and finish dates for project activities?

The Critical Path Method (CPM) is a schedule network analysis technique used to determine the critical path and calculate activity float.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which tool or technique is used to determine the earliest and latest possible start and finish dates for project activities?

Answer options: ✅ Critical Path Method (CPM)

  • Resource Leveling
  • What-if scenario analysis
  • Crashing

Correct answer: Critical Path Method (CPM)

Explanation: The Critical Path Method (CPM) is a schedule network analysis technique used to determine the critical path and calculate activity float.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.