A CPI (Cost Performance Index) of 0.85 indicates that:

A CPI less than 1.0 indicates that the project is over budget for the work completed. For every dollar spent, only 85 cents of work value was received.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A CPI (Cost Performance Index) of 0.85 indicates that:

Answer options:

  • The project is under budget ✅ The project is over budget
  • The project is ahead of schedule
  • The project is behind schedule

Correct answer: The project is over budget

Explanation: A CPI less than 1.0 indicates that the project is over budget for the work completed. For every dollar spent, only 85 cents of work value was received.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.