Which document describes how the project schedule will be managed, including scheduling methodology, tools, and control thresholds?

The schedule management plan defines the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project sche

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which document describes how the project schedule will be managed, including scheduling methodology, tools, and control thresholds?

Answer options:

  • Project management plan
  • Schedule baseline
  • Activity list ✅ Schedule management plan

Correct answer: Schedule management plan

Explanation: The schedule management plan defines the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.