Skip to main content

PMP (Project Management Professional) · Question

A project manager is developing a cost estimate when there is a limited amount of detailed information available. Which estimation technique is most appropriate?

Analogous estimating uses historical data from a previous, similar project and is often used when there is limited detailed information early in the project.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A project manager is developing a cost estimate when there is a limited amount of detailed information available. Which estimation technique is most appropriate?

Answer options: ✅ Analogous estimating

  • Bottom-up estimating
  • Parametric estimating
  • Three-point estimating

Correct answer: Analogous estimating

Explanation: Analogous estimating uses historical data from a previous, similar project and is often used when there is limited detailed information early in the project.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.