Which of the following describes the most restrictive scheduling relationship where an activity cannot start until the preceding activity is finished?

Finish-to-Start (FS) is the most common and restrictive dependency, meaning the successor activity cannot start until the predecessor activity is complete.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which of the following describes the most restrictive scheduling relationship where an activity cannot start until the preceding activity is finished?

Answer options: ✅ Finish-to-Start (FS)

  • Start-to-Start (SS)
  • Finish-to-Finish (FF)
  • Start-to-Finish (SF)

Correct answer: Finish-to-Start (FS)

Explanation: Finish-to-Start (FS) is the most common and restrictive dependency, meaning the successor activity cannot start until the predecessor activity is complete.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.