What does a negative value for the Schedule Variance (SV) indicate?

Schedule Variance (SV = EV - PV). A negative SV means the earned value (EV) is less than the planned value (PV), indicating behind schedule.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What does a negative value for the Schedule Variance (SV) indicate?

Answer options: ✅ The project is behind schedule.

  • The project is ahead of schedule.
  • The project is over budget.
  • The project is under budget.

Correct answer: The project is behind schedule.

Explanation: Schedule Variance (SV = EV - PV). A negative SV means the earned value (EV) is less than the planned value (PV), indicating behind schedule.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.