PMP (Project Management Professional) · Question
What is the primary purpose of creating a Work Breakdown Structure (WBS)?
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives and create the require
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: What is the primary purpose of creating a Work Breakdown Structure (WBS)?
Answer options: ✅ To decompose project scope into smaller, manageable components.
- To define activity dependencies and critical path.
- To estimate activity durations and resource requirements.
- To track project costs against baselines.
Correct answer: To decompose project scope into smaller, manageable components.
Explanation: The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives and create the required deliverables.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.