Which technique is used to determine the early start, early finish, late start, and late finish dates for all activities in a project schedule?

CPM calculates the longest path of planned activities to the end of the project, and the earliest and latest possible start and finish times for activities.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which technique is used to determine the early start, early finish, late start, and late finish dates for all activities in a project schedule?

Answer options: ✅ Critical Path Method (CPM)

  • Program Evaluation and Review Technique (PERT)
  • Resource Leveling
  • Monte Carlo Simulation

Correct answer: Critical Path Method (CPM)

Explanation: CPM calculates the longest path of planned activities to the end of the project, and the earliest and latest possible start and finish times for activities.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.