PMP (Project Management Professional) · Question
Which technique is used to determine the early start, early finish, late start, and late finish dates for all activities in a project schedule?
CPM calculates the longest path of planned activities to the end of the project, and the earliest and latest possible start and finish times for activities.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: Which technique is used to determine the early start, early finish, late start, and late finish dates for all activities in a project schedule?
Answer options: ✅ Critical Path Method (CPM)
- Program Evaluation and Review Technique (PERT)
- Resource Leveling
- Monte Carlo Simulation
Correct answer: Critical Path Method (CPM)
Explanation: CPM calculates the longest path of planned activities to the end of the project, and the earliest and latest possible start and finish times for activities.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.