What is the term for funds allocated to address risks that are identified but cannot be specifically planned for?

Management reserves are for unknown-unknown risks, providing funds for unforeseen changes to project scope and cost.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the term for funds allocated to address risks that are identified but cannot be specifically planned for?

Answer options: ✅ Management Reserve

  • Contingency Reserve
  • Cost Baseline
  • Estimate at Completion (EAC)

Correct answer: Management Reserve

Explanation: Management reserves are for unknown-unknown risks, providing funds for unforeseen changes to project scope and cost.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.