PMP (Project Management Professional) · Question

A project manager is prioritizing risks based on their probability of occurrence and impact. Which risk management tool or technique are they using?

A Risk Matrix, also known as a Probability and Impact Matrix, is commonly used to prioritize individual project risks based on their likelihood and potential ef

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A project manager is prioritizing risks based on their probability of occurrence and impact. Which risk management tool or technique are they using?

Answer options: ✅ Risk Matrix (Probability and Impact Matrix)

  • SWOT Analysis
  • Decision Tree Analysis
  • Expected Monetary Value (EMV) Analysis

Correct answer: Risk Matrix (Probability and Impact Matrix)

Explanation: A Risk Matrix, also known as a Probability and Impact Matrix, is commonly used to prioritize individual project risks based on their likelihood and potential effect.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.