PMP (Project Management Professional) · Question
What is the primary benefit of using a Reserve Analysis technique in Cost Management?
Reserve analysis involves estimating contingency reserves and management reserves to account for cost uncertainty and known and unknown risks.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: What is the primary benefit of using a Reserve Analysis technique in Cost Management?
Answer options: ✅ To account for cost uncertainty and potential risks
- To track actual costs against the budget baseline
- To optimize resource allocation across project activities
- To identify cost savings opportunities
Correct answer: To account for cost uncertainty and potential risks
Explanation: Reserve analysis involves estimating contingency reserves and management reserves to account for cost uncertainty and known and unknown risks.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.