PMP (Project Management Professional) · Question

Which stakeholder engagement level describes stakeholders who are aware of the project and actively supportive?

Supportive stakeholders are aware of the project and its potential impacts and are actively supportive of the project's success.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which stakeholder engagement level describes stakeholders who are aware of the project and actively supportive?

Answer options:

  • Unaware
  • Resistant
  • Neutral ✅ Supportive

Correct answer: Supportive

Explanation: Supportive stakeholders are aware of the project and its potential impacts and are actively supportive of the project's success.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.