What is the critical path in a project schedule?
The critical path is the longest sequence of activities that must be completed on time for the project to be completed by its due date. Any delay on the critica
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: What is the critical path in a project schedule?
Answer options:
- The sequence of activities with the highest cost
- The shortest possible duration to complete the project ✅ The longest path of scheduled activities that determines the project's shortest completion time
- The path with the most resources assigned
Correct answer: The longest path of scheduled activities that determines the project's shortest completion time
Explanation: The critical path is the longest sequence of activities that must be completed on time for the project to be completed by its due date. Any delay on the critical path will delay the entire project.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.