What is the critical path in a project schedule?

The critical path is the longest sequence of activities that must be completed on time for the project to be completed by its due date. Any delay on the critica

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the critical path in a project schedule?

Answer options:

  • The sequence of activities with the highest cost
  • The shortest possible duration to complete the project ✅ The longest path of scheduled activities that determines the project's shortest completion time
  • The path with the most resources assigned

Correct answer: The longest path of scheduled activities that determines the project's shortest completion time

Explanation: The critical path is the longest sequence of activities that must be completed on time for the project to be completed by its due date. Any delay on the critical path will delay the entire project.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.