What does a Cost Performance Index (CPI) of less than 1.0 indicate?

A CPI less than 1.0 means that the project is getting less value than planned for the actual cost incurred, indicating an over-budget status.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What does a Cost Performance Index (CPI) of less than 1.0 indicate?

Answer options: ✅ The project is over budget

  • The project is under budget
  • The project is ahead of schedule
  • The project is behind schedule

Correct answer: The project is over budget

Explanation: A CPI less than 1.0 means that the project is getting less value than planned for the actual cost incurred, indicating an over-budget status.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.