Which of the following is an output of 'Collect Requirements'?

The Requirements Traceability Matrix is an output of Collect Requirements, linking requirements to their origin and tracking them throughout the project life cy

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which of the following is an output of 'Collect Requirements'?

Answer options:

  • Requirements Management Plan ✅ Requirements Traceability Matrix
  • Work Breakdown Structure
  • Project Scope Statement

Correct answer: Requirements Traceability Matrix

Explanation: The Requirements Traceability Matrix is an output of Collect Requirements, linking requirements to their origin and tracking them throughout the project life cycle.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.