PMP (Project Management Professional) · Question
A project manager is experiencing frequent changes to project requirements. Which schedule compression technique would be LEAST suitable for this situation?
Resource leveling adjusts the schedule to optimize resource utilization, potentially extending the project duration, which doesn't directly address frequent req
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: A project manager is experiencing frequent changes to project requirements. Which schedule compression technique would be LEAST suitable for this situation?
Answer options:
- Crashing
- Fast Tracking ✅ Resource Leveling
- Schedule Network Analysis
Correct answer: Resource Leveling
Explanation: Resource leveling adjusts the schedule to optimize resource utilization, potentially extending the project duration, which doesn't directly address frequent requirement changes for schedule compression.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.