A project manager is experiencing frequent changes to project requirements. Which schedule compression technique would be LEAST suitable for this situation?

Resource leveling adjusts the schedule to optimize resource utilization, potentially extending the project duration, which doesn't directly address frequent req

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A project manager is experiencing frequent changes to project requirements. Which schedule compression technique would be LEAST suitable for this situation?

Answer options:

  • Crashing
  • Fast Tracking ✅ Resource Leveling
  • Schedule Network Analysis

Correct answer: Resource Leveling

Explanation: Resource leveling adjusts the schedule to optimize resource utilization, potentially extending the project duration, which doesn't directly address frequent requirement changes for schedule compression.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.