Which document provides a summary of estimated costs for individual work packages and control accounts?

The cost baseline is the approved version of the time-phased project budget, including management reserves, used to measure and monitor cost performance.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which document provides a summary of estimated costs for individual work packages and control accounts?

Answer options: ✅ Cost baseline

  • Cost management plan
  • Project budget
  • Funding limit reconciliation

Correct answer: Cost baseline

Explanation: The cost baseline is the approved version of the time-phased project budget, including management reserves, used to measure and monitor cost performance.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.