Which cost management process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Control Costs is the process where actual costs are monitored, variances are managed, and the cost baseline is updated as necessary to keep the project on track

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which cost management process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Answer options: ✅ Control Costs

  • Estimate Costs
  • Plan Cost Management
  • Determine Budget

Correct answer: Control Costs

Explanation: Control Costs is the process where actual costs are monitored, variances are managed, and the cost baseline is updated as necessary to keep the project on track.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.