PMP (Project Management Professional) · Question
Which cost management process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
Control Costs is the process where actual costs are monitored, variances are managed, and the cost baseline is updated as necessary to keep the project on track
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: Which cost management process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
Answer options: ✅ Control Costs
- Estimate Costs
- Plan Cost Management
- Determine Budget
Correct answer: Control Costs
Explanation: Control Costs is the process where actual costs are monitored, variances are managed, and the cost baseline is updated as necessary to keep the project on track.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.