PMP (Project Management Professional) · Question
What is 'Fast Tracking' in schedule compression?
Fast tracking is a schedule compression technique where activities or phases that are normally done in sequence are performed in parallel for at least a portion
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: What is 'Fast Tracking' in schedule compression?
Answer options:
- Adding more resources to critical path activities to shorten duration ✅ Performing activities in parallel that were originally planned sequentially
- Reducing the scope of work to meet the deadline
- Removing non-critical activities from the schedule
Correct answer: Performing activities in parallel that were originally planned sequentially
Explanation: Fast tracking is a schedule compression technique where activities or phases that are normally done in sequence are performed in parallel for at least a portion of their duration.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.