What is 'Fast Tracking' in schedule compression?

Fast tracking is a schedule compression technique where activities or phases that are normally done in sequence are performed in parallel for at least a portion

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is 'Fast Tracking' in schedule compression?

Answer options:

  • Adding more resources to critical path activities to shorten duration ✅ Performing activities in parallel that were originally planned sequentially
  • Reducing the scope of work to meet the deadline
  • Removing non-critical activities from the schedule

Correct answer: Performing activities in parallel that were originally planned sequentially

Explanation: Fast tracking is a schedule compression technique where activities or phases that are normally done in sequence are performed in parallel for at least a portion of their duration.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.