A project manager is using a schedule compression technique that involves adding more resources to activities on the critical path. What is this technique called?

Crashing is a schedule compression technique where resources are added to activities to shorten their duration, often at an increased cost.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A project manager is using a schedule compression technique that involves adding more resources to activities on the critical path. What is this technique called?

Answer options: ✅ Crashing

  • Fast tracking
  • Resource leveling
  • Schedule baselining

Correct answer: Crashing

Explanation: Crashing is a schedule compression technique where resources are added to activities to shorten their duration, often at an increased cost.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.