What does a negative schedule variance (SV) indicate?

A negative schedule variance (EV - PV) means that the earned value is less than the planned value, indicating the project is behind schedule.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What does a negative schedule variance (SV) indicate?

Answer options: ✅ The project is behind schedule

  • The project is ahead of schedule
  • The project is over budget
  • The project is under budget

Correct answer: The project is behind schedule

Explanation: A negative schedule variance (EV - PV) means that the earned value is less than the planned value, indicating the project is behind schedule.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.