PMP (Project Management Professional) · Question

What is the primary document used to define the project's objectives, deliverables, and requirements in detail?

The scope baseline, comprising the scope statement, WBS, and WBS dictionary, provides the detailed definition of the project's scope.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the primary document used to define the project's objectives, deliverables, and requirements in detail?

Answer options:

  • Project charter ✅ Scope baseline
  • Work Breakdown Structure (WBS)
  • Project management plan

Correct answer: Scope baseline

Explanation: The scope baseline, comprising the scope statement, WBS, and WBS dictionary, provides the detailed definition of the project's scope.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.