PMP (Project Management Professional) · Question

In an agile project, what is the primary purpose of a 'sprint review'?

The sprint review is a formal opportunity to inspect the increment with stakeholders and adjust the product backlog based on feedback. It focuses on the product

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: In an agile project, what is the primary purpose of a 'sprint review'?

Answer options: ✅ To inspect the increment and adapt the product backlog if needed.

  • To discuss team performance and process improvements.
  • To refine the product backlog for future sprints.
  • To assign tasks for the next sprint.

Correct answer: To inspect the increment and adapt the product backlog if needed.

Explanation: The sprint review is a formal opportunity to inspect the increment with stakeholders and adjust the product backlog based on feedback. It focuses on the product being built.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.