Which document is used to record and track the outcome of the risk identification and analysis process?

The risk register is a document in which the results of risk analysis and risk response planning are recorded. It serves as a central repository for all identif

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which document is used to record and track the outcome of the risk identification and analysis process?

Answer options: ✅ Risk Register

  • Issue Log
  • Risk Management Plan
  • Stakeholder Register

Correct answer: Risk Register

Explanation: The risk register is a document in which the results of risk analysis and risk response planning are recorded. It serves as a central repository for all identified risks.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.