What is the purpose of a 'probability and impact matrix' in risk management?

A probability and impact matrix is used to assess and prioritize individual project risks based on their probability of occurrence and the potential impact they

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the purpose of a 'probability and impact matrix' in risk management?

Answer options:

  • To categorize stakeholder engagement levels ✅ To prioritize individual project risks
  • To determine project funding limits
  • To track project schedule variances

Correct answer: To prioritize individual project risks

Explanation: A probability and impact matrix is used to assess and prioritize individual project risks based on their probability of occurrence and the potential impact they would have on project objectives.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.