PMP (Project Management Professional) · Question
In a predictive project, what is the main purpose of the 'Close Project or Phase' process?
The Close Project or Phase process finalizes all activities across all of the Project Management Process Groups to formally complete the project or phase.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: In a predictive project, what is the main purpose of the 'Close Project or Phase' process?
Answer options: ✅ To formally finalize all project activities and contractual obligations.
- To identify, analyze, and plan for project risks.
- To develop the project schedule and cost baselines.
- To execute project work and produce deliverables.
Correct answer: To formally finalize all project activities and contractual obligations.
Explanation: The Close Project or Phase process finalizes all activities across all of the Project Management Process Groups to formally complete the project or phase.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.