A project manager is creating a network diagram to determine the longest path through the project. What is this path called?

The critical path is the sequence of activities that represents the longest path through a project, determining the shortest possible project duration.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A project manager is creating a network diagram to determine the longest path through the project. What is this path called?

Answer options: ✅ Critical path

  • Fast track path
  • Float path
  • Resource-constrained path

Correct answer: Critical path

Explanation: The critical path is the sequence of activities that represents the longest path through a project, determining the shortest possible project duration.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.