PMP (Project Management Professional) · Question
Which of the following best describes the critical path of a project?
The critical path is the longest sequence of activities in a project plan, which must be completed on time for the project to finish on schedule.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: Which of the following best describes the critical path of a project?
Answer options: ✅ The longest path through the project network diagram, determining the shortest possible project duration
- The sequence of activities with the highest risk
- The path with the most float or slack time
- The activities that can be delayed without affecting the project end date
Correct answer: The longest path through the project network diagram, determining the shortest possible project duration
Explanation: The critical path is the longest sequence of activities in a project plan, which must be completed on time for the project to finish on schedule.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.