Which of the following best describes the critical path of a project?

The critical path is the longest sequence of activities in a project plan, which must be completed on time for the project to finish on schedule.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which of the following best describes the critical path of a project?

Answer options: ✅ The longest path through the project network diagram, determining the shortest possible project duration

  • The sequence of activities with the highest risk
  • The path with the most float or slack time
  • The activities that can be delayed without affecting the project end date

Correct answer: The longest path through the project network diagram, determining the shortest possible project duration

Explanation: The critical path is the longest sequence of activities in a project plan, which must be completed on time for the project to finish on schedule.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.