PMP (Project Management Professional) · Question
What is the primary indicator of project performance using Earned Value Management (EVM) that measures schedule efficiency?
The Schedule Performance Index (SPI) is an EVM metric that indicates the schedule efficiency of the project.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: What is the primary indicator of project performance using Earned Value Management (EVM) that measures schedule efficiency?
Answer options:
- Schedule Variance (SV)
- Cost Variance (CV) ✅ Schedule Performance Index (SPI)
- Cost Performance Index (CPI)
Correct answer: Schedule Performance Index (SPI)
Explanation: The Schedule Performance Index (SPI) is an EVM metric that indicates the schedule efficiency of the project.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.