What is the primary indicator of project performance using Earned Value Management (EVM) that measures schedule efficiency?

The Schedule Performance Index (SPI) is an EVM metric that indicates the schedule efficiency of the project.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the primary indicator of project performance using Earned Value Management (EVM) that measures schedule efficiency?

Answer options:

  • Schedule Variance (SV)
  • Cost Variance (CV) ✅ Schedule Performance Index (SPI)
  • Cost Performance Index (CPI)

Correct answer: Schedule Performance Index (SPI)

Explanation: The Schedule Performance Index (SPI) is an EVM metric that indicates the schedule efficiency of the project.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.