PMP (Project Management Professional) · Question
In an Agile project, what is the primary purpose of a Sprint Review?
The Sprint Review is held at the end of the Sprint to inspect the increment and adapt the Product Backlog if needed. It is a key feedback loop.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: In an Agile project, what is the primary purpose of a Sprint Review?
Answer options: ✅ To inspect the increment and adapt the product backlog if needed.
- To improve team processes and work practices.
- To estimate remaining work and plan for the next sprint.
- To discuss and resolve technical challenges encountered.
Correct answer: To inspect the increment and adapt the product backlog if needed.
Explanation: The Sprint Review is held at the end of the Sprint to inspect the increment and adapt the Product Backlog if needed. It is a key feedback loop.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.