Which earned value management (EVM) metric indicates how efficiently the project budget is being used?

The Cost Performance Index (CPI) measures the cost efficiency of the budget spent for the work completed, reflecting how efficiently the budget is being utilize

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which earned value management (EVM) metric indicates how efficiently the project budget is being used?

Answer options:

  • Schedule Performance Index (SPI) ✅ Cost Performance Index (CPI)
  • Estimate at Completion (EAC)
  • Variance at Completion (VAC)

Correct answer: Cost Performance Index (CPI)

Explanation: The Cost Performance Index (CPI) measures the cost efficiency of the budget spent for the work completed, reflecting how efficiently the budget is being utilized.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.