In a Scrum framework, who is responsible for managing the product backlog and maximizing the value of the product?

The Product Owner is responsible for maximizing the value of the product and managing the Product Backlog.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: In a Scrum framework, who is responsible for managing the product backlog and maximizing the value of the product?

Answer options:

  • Scrum Master
  • Development Team ✅ Product Owner
  • Project Manager

Correct answer: Product Owner

Explanation: The Product Owner is responsible for maximizing the value of the product and managing the Product Backlog.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.