A stakeholder with high power and low interest should be:

Power/Interest grid: high power, low interest = keep satisfied.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A stakeholder with high power and low interest should be:

Answer options:

  • Managed closely ✅ Kept satisfied
  • Kept informed
  • Monitored

Correct answer: Kept satisfied

Explanation: Power/Interest grid: high power, low interest = keep satisfied.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.