EVM: PV=100, EV=80, AC=90. SPI and CPI are:
SPI=EV/PV=0.80; CPI=EV/AC=0.89.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
Question: EVM: PV=100, EV=80, AC=90. SPI and CPI are:
Answer options:
- 1.25 and 1.13 ✅ 0.80 and 0.89
- 0.89 and 0.80
- 1.13 and 1.25
Correct answer: 0.80 and 0.89
Explanation: SPI=EV/PV=0.80; CPI=EV/AC=0.89.
Start free practice for PMP (Project Management Professional)
200 questions · no signup required · 40 free questions per day
More about PMP (Project Management Professional)
Related Questions
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
- In an agile project, who is primarily responsible for prioritizing the product backlog?
- Which tool or technique is used to determine the earliest and latest possible start and finish dates for proje
More for PMP (Project Management Professional) candidates
Question explanations
- What is the primary output of the 'Direct and Manage Project Work' process?
- Which project management approach emphasizes frequent communication, self-organizing teams, and adapting to ch
- Which of the following is an output of the 'Develop Project Charter' process?
- Which type of risk response strategy involves shifting the impact of a threat along with ownership to a third
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free PMP (Project Management Professional) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.