EVM: PV=100, EV=80, AC=90. SPI and CPI are:

SPI=EV/PV=0.80; CPI=EV/AC=0.89.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: EVM: PV=100, EV=80, AC=90. SPI and CPI are:

Answer options:

  • 1.25 and 1.13 ✅ 0.80 and 0.89
  • 0.89 and 0.80
  • 1.13 and 1.25

Correct answer: 0.80 and 0.89

Explanation: SPI=EV/PV=0.80; CPI=EV/AC=0.89.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.